All ten synthetic documents and their review index were restored. The free plan gave an invited reviewer edit rights, so the read-only requirement failed.
Reviewed
Acceptance checks
1. Contract and mandatory requirements
BlockedThe pilot recorded its synthetic scope and dated requirements. Contract-specific obligations, evidence, owners and authorisation to use real supplier information were still outstanding.
Acceptance criterion
Every mandatory requirement has an evidence reference, date, scope and owner. Any unresolved requirement needed for real data keeps the live gate blocked.
2. Document and review-state recovery
PassedAll ten documents reopened with matching byte counts, SHA-256 hashes, identifiers, revisions and review states. The index reconstructed four drafts, three in review and three reviewed. Prior versions, review actions, audit history and retention were outside the test pack.
Acceptance criterion
For an eventual synthetic rehearsal: 10 of 10 files restore with matching checksums; intended metadata and review states are accounted for; excluded history is explicit.
3. Roles, audit and recovery
FailedThe creator uploaded and accessed the workspace. An uninvited account could see neither file names nor contents. Sync Free gave invited reviewers edit rights, which failed the read-only requirement. The creation event was visible. Account recovery and key management remain open.
Acceptance criterion
Author/reviewer operations work and the denied role cannot view the files. Record audit visibility, account recovery and key-service dependencies.
4. Restore duration and completeness
PassedThe first eight documents arrived in 76.668 s. The provider indicated completion at 120.747 s. All ten documents and the index were available after 2 h 40 min 48 s, including the handoff interval. Complete local verification finished at 2 h 56 min 41 s.
Acceptance criterion
Restore time and completeness are measured. A downloaded archive alone does not establish operational recovery.
5. Approval and boundary of the pilot
PassedThe internal scope identified the sponsor, provider, Canadian file-data region and approved test workspace. It covered ten invented stationery records and their review index. Real supplier data and contract-specific approvals were outside that authorisation. Other processing locations remain unverified.
Acceptance criterion
The exact approvals, entities, deployment and data categories are recorded. No claim of general defence compliance or government endorsement appears in the result.